| Your task | Where to start | What to check |
|---|---|---|
| Price the panelboards | SpecSift · Scope Traps | Read the rejection condition alongside your supplier quote. Ask which replacement costs the quote covers. |
| Hand the estimate to the PM | SpecSift · Submittal Register | Find the product data entry. Check the section and page before requesting the ratings. |
| Build the project log | AutoSpecs · Smart Register | Review the generated submittals. Open Spec View to read an item in its section. |
| Review an addendum | AutoSpecs · Version comparison | Compare the revised book with the previous version and inspect changed submittal requirements. |
Try the same panelboard section
Open Federal Office, section 26 24 16, page 1. Paragraph 1.01 A says, “Submit product data identifying interrupting ratings for each panel.” The PM can use that sentence to request ratings by panel designation.
Paragraph 1.02 A says, “Replace equipment rejected for insufficient fault rating at no additional cost.” Before bid day, ask the supplier, “Which rating did you carry for each panel, and does your quote cover replacement if equipment is rejected for insufficient fault rating?” Record the answer with the quote.
What changed after the base bid?
In the Federal Office sample, the base book asks for each panel’s interrupting rating. Addendum 1 also asks for the available fault current and adds a separate requirement for breaker coordination curves. Open Addendum Diff and read both versions of section 26 24 16 on page 1. Then ask the panelboard supplier whether its quote covers the added submittal work.
For an AutoSpecs evaluation, use the same section in a project log. Locate the product data in Smart Register and trace it back in Spec View. If you have two versions of the book, compare them and see which items need another review. Autodesk workflow guide