| Deliverable | Exact requirement | Source | Owner |
|---|---|---|---|
| Panelboard product data | “Submit product data identifying interrupting ratings for each panel.” | Federal Office · 26 24 16 · 1.01 A · page 1 |
At turnover, agree who will request the sheets and enter that name under Owner. When the sheets arrive, check each panel designation against the rating shown. If one is missing, identify the panel in your follow up.
What belongs in the bid review?
The next paragraph says, “Replace equipment rejected for insufficient fault rating at no additional cost.” Keep that wording with the estimate. Ask the supplier what its quote covers before carrying a replacement cost or assigning it to someone else.
When is the final panelboard schedule due?
On the City of Palatka’s Lift Station 16 project, the PM also needs a turnover date tied to field work. Section 26 24 16, paragraph 1.3.A says, “Submit final versions after load balancing.”
| Deliverable | When to submit | Source |
|---|---|---|
| Final panelboard schedules for installation in the panels | After load balancing | Lift Station 16 · 26 24 16 · 1.3.A · PDF page 181 |
Ask at turnover, “Who will update the schedules once load balancing is complete?” Put that person beside the milestone in the register. Read the Palatka project manual, page 181