Construction submittal log Excel template

Start with the book your shop is bidding. Open the workspace, select a sample or upload a readable specification, then choose Export and Download Excel (.xlsx). Open the Submittal Register worksheet. Each row keeps the request beside the words that triggered it.

What goes in one row?

The exported headers are CSI section, Page, Deliverable, Status and Verbatim quote. In the Federal Office sample, look up section 26 24 16 on page 1. The source reads “Submit product data identifying interrupting ratings for each panel.” Give that row to the panel supplier. Before closing it, check that the returned data lists a rating for every panel in your quote.

For the PM handoff, add an owner, a date needed and a date returned in your Excel copy. Set the date needed from the release schedule. Leave the date returned blank until the supplier sends the package.

What does a mechanical row look like?

Open Hospital Clinic and inspect section 23 73 00 on page 1. It reads “Submit shop drawings showing coil pull space and access door swings.” Keep both details in the drawing request. When the drawing arrives, the PM can mark up the service side of the unit and check the door swing before releasing it.

Where do turnover requirements go?

In the Palatka manual, section 01 33 00 on PDF page 134 calls for two bound sets of operation and maintenance manuals before substantial completion unless otherwise specified. Check the individual equipment section before assigning the quantity. Use the milestone to work back to a supplier due date.

Keep open scope questions in the Scope Traps and RFI Log worksheets. A supplier can return panel data while the team still needs an answer about replacement costs. Tracking those separately lets the PM close the document request and carry the cost question into the next bid review.

Open a sample and download its Excel register.